济南停车棚:塔楼底部的施工技术方案!

来源:/ 日期:2025-10-21 发布人:

  1.1.1.概述塔楼底部雨棚属于大型钢结构雨棚,外部包玻璃,内部吊顶部分为不锈钢管格栅。总共包含叁个雨棚,分别位于塔楼的北、南、西侧,的雨棚长度约37.85米,由框架玻璃系统配不锈钢包铝圆管装饰线条、铝板系统组成与塔楼主体单元幕墙系统相呼应,雨棚二次钢结构由我司完成。底层吊顶由不锈钢格栅与钢结构包铝板组成。其中北、南侧雨棚为落地式。塔楼底部雨棚平面位置示意图(粉色部分)塔楼底部南侧雨棚整体效果图塔楼底部南侧雨棚底部效果图塔楼底部雨棚整体安装可靠,造型独特,具有现代的美感,与塔楼整体的装饰效果遥相呼应。雨棚向外倾斜,以便排水,并设有排水沟系统,对此我司采用满堂脚手架进行该雨棚的安装,采用汽车吊进行二次钢件的垂直运输及定位。雨棚施工措施示意图下面详细介绍在施工工艺及施工质量保证方面将做出切实可行的方案。并就具体的施工方案阐述如下:057c5f84-ed06-40c0-8dde-04c6ddf0b5cf

  1.1.1. Overview: The bottom canopy of the tower belongs to a large steel structure canopy, which is covered with glass on the outside and has a stainless steel pipe grille as the internal ceiling. There are a total of three canopies, located on the north, south, and west sides of the tower. The largest canopy is approximately 37.85 meters long and consists of a frame glass system with stainless steel wrapped aluminum circular pipe decorative lines and an aluminum panel system that corresponds to the main unit curtain wall system of the tower. The secondary steel structure of the canopy is completed by our company. The bottom ceiling is composed of stainless steel grating and steel structure wrapped with aluminum plate. The north and south canopies are floor standing. Schematic diagram of the location of the rain shelter at the bottom of the tower (pink part) Overall rendering of the rain shelter on the south side of the tower bottom Overall rendering of the rain shelter on the south side of the tower bottom Overall installation of the rain shelter at the bottom of the tower is reliable, with a unique shape and modern beauty, echoing the overall decorative effect of the tower. The canopy slopes outward for drainage and is equipped with a drainage ditch system. Our company uses a full scaffold for the installation of the canopy and a truck crane for the vertical transportation and positioning of secondary steel components. The schematic diagram of the construction measures for the canopy below provides a detailed introduction to the practical and feasible plans that will be made in terms of construction technology and quality assurance. And the specific construction plan is explained as follows:

  1.1.2.施工工艺流程控制线测设→钢结构检查→现场人员和设施准备→雨棚钢骨架结构误差测量→玻璃安装→不锈钢板、铝板安装→注胶→不锈钢管安装→验收

  1.1.2. Construction process control line measurement → Steel structure inspection → On site personnel and facility preparation → Error measurement of canopy steel skeleton structure → Glass installation → Installation of stainless steel plates and aluminum plates → Glue injection → Installation of stainless steel pipes → Acceptance

  1.1.3.具体的施工方法1.1.3.1.控制线测设

  1.1.3. Specific construction methods 1.1.3.1. Control line measurement and setting

  (1)、与总承包单位确定好基准线和水准点,再用经纬仪放出控制线以及拐角控制线。

  (1) Firstly, determine the baseline and benchmark with the general contracting unit, and then use a theodolite to set out the control line and corner control line.

  (2)、将土建单位提供的基准中心线、水平线进行复测,无误后放钢线,定出幕墙安装基准线。为保证不受其它因素影响,放完线后,用全站仪检测,调准。

  (2) Re measure the reference center line and horizontal line provided by the civil engineering unit, and after confirming their accuracy, lay out the steel line to determine the installation reference line for the curtain wall. To ensure that it is not affected by other factors, after laying out the line, use a total station to detect and adjust it accurately.

  (3)、由于本工程雨棚安装时搭设满堂脚手架进行施工,根据施工图投测出地面定测点,再搭设脚手架,然后依据地面定测点,使用激光垂准仪和采用拉线法将地面定测点投测到脚手架搭设平台,确定钢构件安装位置。

  (3) Due to the installation of the rain shelter in this project, a full scaffold was set up for construction. Based on the construction drawings, the ground measurement points were measured, and then the scaffold was erected. Then, according to the ground measurement points, a laser plumb line and a wire drawing method were used to project the ground measurement points onto the scaffold erection platform to determine the installation position of the steel components.

  (4)、测设出的控制点,用红漆标示,并加以保护。测设出的水平控制点,应设置在性的结构上,用红漆清楚注明标高。

  (4) The control points set up shall be marked with red paint and protected. The horizontal control points established through measurement should be set on permanent structures, and the elevation should be clearly marked with red paint.

  1.1.3.2.钢结构检查

  1.1.3.2. Steel structure inspection

  (1)、经过测量放样得到幕墙结构实际的确切位置后,应该根据钢结构支撑布置图,校准钢构件的位置。

  (1) After measuring and laying out the actual position of the curtain wall structure, the position of the steel components should be calibrated according to the steel structure support layout plan.

  (2)、如果结构尺寸有偏离,须进行重新处理的,通知有关方可进行结构调整,直达到幕墙要求的精度。

  (2) If there is a deviation in the structural dimensions that requires reprocessing, notify the relevant parties to make structural adjustments until the required accuracy of the curtain wall is achieved.

  1.1.3.3.搭设满堂脚手架在雨棚底部搭设满堂脚手架。

  1.1.3.3. Set up full scaffolding at the bottom of the canopy.

  1.1.3.4.构件加工图设计依据施工图纸资料,结合结构检查和测量放样的数据,进行雨棚加工图构件加工图设计。内容应包括但不限于《雨棚钢结构件加工图》、《雨棚玻璃加工图》、《雨棚装饰铝板加工图》、《雨棚角码加工图》、《雨棚焊接工艺图》、《雨棚辅材加工及提料单》等等。

  1.1.3.4. The design of component processing drawings is based on construction drawing data, combined with structural inspection and measurement layout data, to carry out the design of canopy processing drawings and component processing drawings. The content should include but not limited to "Processing Drawing of Rainshed Steel Structure Components", "Processing Drawing of Rainshed Glass", "Processing Drawing of Rainshed Decorative Aluminum Plate", "Processing Drawing of Rainshed Corner Code", "Welding Process Drawing of Rainshed", "Processing and Material Supply List of Rainshed Auxiliary Materials", etc.

  1.1.3.5.构件加工及组装构件加工是生产部门严格按照生产加工操作程序进行的。操作程序是指生产部从接受任务到成品现场全过程的生产活动和控制手段。可分为以下几个阶段:

  1.1.3.5. Component processing and assembly component processing are strictly carried out by the production department in accordance with the production processing operation procedures. Operating procedures refer to the production activities and control measures of the production department throughout the entire process from receiving tasks to producing finished products on site. It can be divided into the following stages:

  (1)、接受任务和下达任务项目管理中心将加工图分类送工厂相应的车间,制定生产加工计划,将相关任务计划下达到各加工车间。

  (1) The project management center will classify and send the processing drawings to the corresponding workshops in the factory, formulate production and processing plans, and issue relevant task plans to each processing workshop.

  (2)、工艺编制和工时定额根据加工图纸,编制各种加工零件的工艺卡片,同时,定额员根据工艺卡制定工时定额。

  (2) According to the processing drawings, process cards for various processed parts are prepared for process planning and time quotas. At the same time, the quota officer formulates time quotas based on the process cards.

  (3)、车间加工车间技术工人按工艺卡、图纸技术要求、质量等级进行机械加工。

  (3) Workshop technicians carry out mechanical processing according to process cards, drawing technical requirements, and quality levels.

  (4)、质量检验在生产的全过程中始终贯穿着质量检验,包括自检、抽检的执行。

  (4) Quality inspection runs through the entire production process, including self inspection and sampling.

  (5)、包装、运输现场完成现场所需要的合格半成品和成品后,即可按照不同的包装要求对不同产物进行包装,并按一定的方法装车运现场。

  (5) After packaging and transporting the qualified semi-finished and finished products required on site, different products can be packaged according to different packaging requirements and loaded onto trucks according to certain methods for transportation to the site.

  1.1.3.6.现场施工人员和施工设施准备

  1.1.3.6. Preparation of on-site construction personnel and construction facilities

  (1)、施工人员安排我司将组织雨棚施工队进行施工,人员配置,施工队长1人,汽车吊司机1人,雨棚施工队员15人(含检测员、信号员、电焊工、机械工、电工和小工等雨棚安装所需的各类工种),预计30个工作日即可完成1个雨棚施工。

  (1) Our company will organize a professional canopy construction team to carry out the construction. The team will consist of one construction team leader, one truck crane driver, and 15 professional canopy construction team members (including inspectors, signalers, welders, mechanics, electricians, and laborers). It is expected that one canopy construction can be completed in 30 working days.

  (2)、施工设施准备采用汽车吊对较大钢结构构件的进行吊装,用手动葫芦辅助吊装。另应准备电焊机、打磨机3台、手电钻、注胶枪、测量放线设备、油漆等各种雨棚施工队常用的小型施工设备及辅助材料等,均应在施工前准备到位。

  (2) The construction facilities are prepared to use a truck crane to lift larger steel structural components, with manual hoists assisting in the lifting process. In addition, various small construction equipment and auxiliary materials commonly used by the canopy construction team, such as welding machines, polishing machines, hand drills, glue guns, measuring and laying out equipment, paint, etc., should be prepared in place before construction.

  1.1.3.7.雨棚钢骨架安装

  1.1.3.7. Installation of canopy steel frame

  (1)待全部材料进场且检验合格,现场施工人员和施工设施准备妥当,即可进行雨棚钢骨架构件安装,雨棚安装的主要技术依据为《依据测量放样数据》、《施工图》、《雨棚加工图》、《雨棚安装现场技术及交底》等。

  (1) After all materials have entered the site and passed the inspection, and the on-site construction personnel and facilities are ready, the installation of the steel frame components for the canopy can be carried out. The main technical basis for canopy installation is "Based on Measurement and Layout Data", "Construction Drawings", "Canopy Processing Drawings", "Canopy Installation Site Technical and Safety Disclosure", etc.

  (2)用汽车吊吊起钢通,将雨棚钢结构高度调整确定后,即可进行钢结构的焊接。根据定位线确定钢结构的标高,先焊接主龙骨钢通,再焊接横向次龙骨钢通,进行边部造型处的钢结构。

  (2) Lift the steel pipe with a car crane, adjust the height of the canopy steel structure to determine, and then proceed with welding the steel structure. Determine the elevation of the steel structure based on the positioning line, first weld the main keel steel through, then weld the horizontal secondary keel steel through, and finally proceed with the steel structure at the edge shaping.

  1.1.3.8.雨棚钢骨架结构误差测量和隐蔽验收完成雨棚钢骨架安装后,填写《隐蔽验收单》附《雨棚钢骨架结构检查表》报监理单位验收。

  1.1.3.8. Error measurement and concealed acceptance of canopy steel frame structure. After the installation of canopy steel frame is completed, fill out the "Concealed Acceptance Form" and attach the "Canopy Steel Frame Structure Inspection Form" to report to the supervision unit for acceptance.

  1.1.3.9.面板安装待钢骨架安装验收完毕后,采用汽车吊及电动吸盘进行玻璃面板的吊装,利用满堂脚手架安装玻璃。

  1.1.3.9. After the installation and acceptance of the steel frame, the glass panel will be lifted using a truck crane and electric suction cup, and the glass will be installed using a full scaffold.

  (1)、在龙骨上重新弹设玻璃安装中心定位线,所弹墨线几何尺寸应符合要求,墨线必须清晰。

  (1) Re mark the glass installation center positioning line on the keel, and the geometric dimensions of the marked ink line should meet the requirements. The ink line must be clear.

  (2)、依据《雨棚玻璃编号图》,确定每块玻璃在雨棚上的位置,安装前位控制线,因雨棚钢结构总有一些不平整,玻璃支撑点处需进行调整垫平。

  (2) According to the "Rainshed Glass Number Diagram", determine the position of each glass on the canopy and install the front control line. Due to the unevenness of the canopy steel structure, the glass support points need to be adjusted and leveled.

  1.1.3.10.雨棚吊顶安装待注胶等防水密封措施施工完毕,采用满堂脚手架进行不锈钢格栅的安装。雨棚不锈钢格栅吊顶安装示意图

  1.1.3.10. After the installation of waterproof sealing measures such as glue injection for the canopy ceiling is completed, the stainless steel grating will be installed using a full scaffold. Installation diagram of stainless steel grille ceiling for canopy

  1.1.3.11.安装完成全部安装完成后,进行清洁处理,并做好成品保护标识,防止损坏。

  1.1.3.11. After the installation is completed, clean it thoroughly and label the finished product to prevent damage.

  1.1.1.概述塔楼底部雨棚属于大型钢结构雨棚,外部包玻璃,内部吊顶部分为不锈钢管格栅。总共包含叁个雨棚,分别位于塔楼的北、南、西侧,的雨棚长度约37.85米,由框架玻璃系统配不锈钢包铝圆管装饰线条、铝板系统组成与塔楼主体单元幕墙系统相呼应,雨棚二次钢结构由我司完成。底层吊顶由不锈钢格栅与钢结构包铝板组成。其中北、南侧雨棚为落地式。塔楼底部雨棚平面位置示意图(粉色部分)塔楼底部南侧雨棚整体效果图塔楼底部南侧雨棚底部效果图塔楼底部雨棚整体安装可靠,造型独特,具有现代的美感,与塔楼整体的装饰效果遥相呼应。雨棚向外倾斜,以便排水,并设有排水沟系统,对此我司采用满堂脚手架进行该雨棚的安装,采用汽车吊进行二次钢件的垂直运输及定位。雨棚施工措施示意图下面详细介绍在施工工艺及施工质量保证方面将做出切实可行的方案。并就具体的施工方案阐述如下:

  1.1.1. Overview: The bottom canopy of the tower belongs to a large steel structure canopy, which is covered with glass on the outside and has a stainless steel pipe grille as the internal ceiling. There are a total of three canopies, located on the north, south, and west sides of the tower. The largest canopy is approximately 37.85 meters long and consists of a frame glass system with stainless steel wrapped aluminum circular pipe decorative lines and an aluminum panel system that corresponds to the main unit curtain wall system of the tower. The secondary steel structure of the canopy is completed by our company. The bottom ceiling is composed of stainless steel grating and steel structure wrapped with aluminum plate. The north and south canopies are floor standing. Schematic diagram of the location of the rain shelter at the bottom of the tower (pink part) Overall rendering of the rain shelter on the south side of the tower bottom Overall rendering of the rain shelter on the south side of the tower bottom Overall installation of the rain shelter at the bottom of the tower is reliable, with a unique shape and modern beauty, echoing the overall decorative effect of the tower. The canopy slopes outward for drainage and is equipped with a drainage ditch system. Our company uses a full scaffold for the installation of the canopy and a truck crane for the vertical transportation and positioning of secondary steel components. The schematic diagram of the construction measures for the canopy below provides a detailed introduction to the practical and feasible plans that will be made in terms of construction technology and quality assurance. And the specific construction plan is explained as follows:

  1.1.2.施工工艺流程控制线测设→钢结构检查→现场人员和设施准备→雨棚钢骨架结构误差测量→玻璃安装→不锈钢板、铝板安装→注胶→不锈钢管安装→验收

  1.1.2. Construction process control line measurement → Steel structure inspection → On site personnel and facility preparation → Error measurement of canopy steel skeleton structure → Glass installation → Installation of stainless steel plates and aluminum plates → Glue injection → Installation of stainless steel pipes → Acceptance

  1.1.3.具体的施工方法1.1.3.1.控制线测设

  1.1.3. Specific construction methods 1.1.3.1. Control line measurement and setting

  (1)、与总承包单位确定好基准线和水准点,再用经纬仪放出控制线以及拐角控制线。

  (1) Firstly, determine the baseline and benchmark with the general contracting unit, and then use a theodolite to set out the control line and corner control line.

  (2)、将土建单位提供的基准中心线、水平线进行复测,无误后放钢线,定出幕墙安装基准线。为保证不受其它因素影响,放完线后,用全站仪检测,调准。

  (2) Re measure the reference center line and horizontal line provided by the civil engineering unit, and after confirming their accuracy, lay out the steel line to determine the installation reference line for the curtain wall. To ensure that it is not affected by other factors, after laying out the line, use a total station to detect and adjust it accurately.

  (3)、由于本工程雨棚安装时搭设满堂脚手架进行施工,根据施工图投测出地面定测点,再搭设脚手架,然后依据地面定测点,使用激光垂准仪和采用拉线法将地面定测点投测到脚手架搭设平台,确定钢构件安装位置。

  (3) Due to the installation of the rain shelter in this project, a full scaffold was set up for construction. Based on the construction drawings, the ground measurement points were measured, and then the scaffold was erected. Then, according to the ground measurement points, a laser plumb line and a wire drawing method were used to project the ground measurement points onto the scaffold erection platform to determine the installation position of the steel components.

  (4)、测设出的控制点,用红漆标示,并加以保护。测设出的水平控制点,应设置在性的结构上,用红漆清楚注明标高。

  (4) The control points set up shall be marked with red paint and protected. The horizontal control points established through measurement should be set on permanent structures, and the elevation should be clearly marked with red paint.

  1.1.3.2.钢结构检查

  1.1.3.2. Steel structure inspection

  (1)、经过测量放样得到幕墙结构实际的确切位置后,应该根据钢结构支撑布置图,校准钢构件的位置。

  (1) After measuring and laying out the actual position of the curtain wall structure, the position of the steel components should be calibrated according to the steel structure support layout plan.

  (2)、如果结构尺寸有偏离,须进行重新处理的,通知有关方可进行结构调整,直达到幕墙要求的精度。

  (2) If there is a deviation in the structural dimensions that requires reprocessing, notify the relevant parties to make structural adjustments until the required accuracy of the curtain wall is achieved.

  1.1.3.3.搭设满堂脚手架在雨棚底部搭设满堂脚手架。

  1.1.3.3. Set up full scaffolding at the bottom of the canopy.

  1.1.3.4.构件加工图设计依据施工图纸资料,结合结构检查和测量放样的数据,进行雨棚加工图构件加工图设计。内容应包括但不限于《雨棚钢结构件加工图》、《雨棚玻璃加工图》、《雨棚装饰铝板加工图》、《雨棚角码加工图》、《雨棚焊接工艺图》、《雨棚辅材加工及提料单》等等。

  1.1.3.4. The design of component processing drawings is based on construction drawing data, combined with structural inspection and measurement layout data, to carry out the design of canopy processing drawings and component processing drawings. The content should include but not limited to "Processing Drawing of Rainshed Steel Structure Components", "Processing Drawing of Rainshed Glass", "Processing Drawing of Rainshed Decorative Aluminum Plate", "Processing Drawing of Rainshed Corner Code", "Welding Process Drawing of Rainshed", "Processing and Material Supply List of Rainshed Auxiliary Materials", etc.

  1.1.3.5.构件加工及组装构件加工是生产部门严格按照生产加工操作程序进行的。操作程序是指生产部从接受任务到成品现场全过程的生产活动和控制手段。可分为以下几个阶段:

  1.1.3.5. Component processing and assembly component processing are strictly carried out by the production department in accordance with the production processing operation procedures. Operating procedures refer to the production activities and control measures of the production department throughout the entire process from receiving tasks to producing finished products on site. It can be divided into the following stages:

  (1)、接受任务和下达任务项目管理中心将加工图分类送工厂相应的车间,制定生产加工计划,将相关任务计划下达到各加工车间。

  (1) The project management center will classify and send the processing drawings to the corresponding workshops in the factory, formulate production and processing plans, and issue relevant task plans to each processing workshop.

  (2)、工艺编制和工时定额根据加工图纸,编制各种加工零件的工艺卡片,同时,定额员根据工艺卡制定工时定额。

  (2) According to the processing drawings, process cards for various processed parts are prepared for process planning and time quotas. At the same time, the quota officer formulates time quotas based on the process cards.

  (3)、车间加工车间技术工人按工艺卡、图纸技术要求、质量等级进行机械加工。

  (3) Workshop technicians carry out mechanical processing according to process cards, drawing technical requirements, and quality levels.

  (4)、质量检验在生产的全过程中始终贯穿着质量检验,包括自检、抽检的执行。

  (4) Quality inspection runs through the entire production process, including self inspection and sampling.

  (5)、包装、运输现场完成现场所需要的合格半成品和成品后,即可按照不同的包装要求对不同产物进行包装,并按一定的方法装车运现场。

  (5) After packaging and transporting the qualified semi-finished and finished products required on site, different products can be packaged according to different packaging requirements and loaded onto trucks according to certain methods for transportation to the site.

  1.1.3.6.现场施工人员和施工设施准备

  1.1.3.6. Preparation of on-site construction personnel and construction facilities

  (1)、施工人员安排我司将组织雨棚施工队进行施工,人员配置,施工队长1人,汽车吊司机1人,雨棚施工队员15人(含检测员、信号员、电焊工、机械工、电工和小工等雨棚安装所需的各类工种),预计30个工作日即可完成1个雨棚施工。

  (1) Our company will organize a professional canopy construction team to carry out the construction. The team will consist of one construction team leader, one truck crane driver, and 15 professional canopy construction team members (including inspectors, signalers, welders, mechanics, electricians, and laborers). It is expected that one canopy construction can be completed in 30 working days.

  (2)、施工设施准备采用汽车吊对较大钢结构构件的进行吊装,用手动葫芦辅助吊装。另应准备电焊机、打磨机3台、手电钻、注胶枪、测量放线设备、油漆等各种雨棚施工队常用的小型施工设备及辅助材料等,均应在施工前准备到位。

  (2) The construction facilities are prepared to use a truck crane to lift larger steel structural components, with manual hoists assisting in the lifting process. In addition, various small construction equipment and auxiliary materials commonly used by the canopy construction team, such as welding machines, polishing machines, hand drills, glue guns, measuring and laying out equipment, paint, etc., should be prepared in place before construction.

  1.1.3.7.雨棚钢骨架安装

  1.1.3.7. Installation of canopy steel frame

  (1)待全部材料进场且检验合格,现场施工人员和施工设施准备妥当,即可进行雨棚钢骨架构件安装,雨棚安装的主要技术依据为《依据测量放样数据》、《施工图》、《雨棚加工图》、《雨棚安装现场技术及交底》等。

  (1) After all materials have entered the site and passed the inspection, and the on-site construction personnel and facilities are ready, the installation of the steel frame components for the canopy can be carried out. The main technical basis for canopy installation is "Based on Measurement and Layout Data", "Construction Drawings", "Canopy Processing Drawings", "Canopy Installation Site Technical and Safety Disclosure", etc.

  (2)用汽车吊吊起钢通,将雨棚钢结构高度调整确定后,即可进行钢结构的焊接。根据定位线确定钢结构的标高,先焊接主龙骨钢通,再焊接横向次龙骨钢通,进行边部造型处的钢结构。

  (2) Lift the steel pipe with a car crane, adjust the height of the canopy steel structure to determine, and then proceed with welding the steel structure. Determine the elevation of the steel structure based on the positioning line, first weld the main keel steel through, then weld the horizontal secondary keel steel through, and finally proceed with the steel structure at the edge shaping.

  1.1.3.8.雨棚钢骨架结构误差测量和隐蔽验收完成雨棚钢骨架安装后,填写《隐蔽验收单》附《雨棚钢骨架结构检查表》报监理单位验收。

  1.1.3.8. Error measurement and concealed acceptance of canopy steel frame structure. After the installation of canopy steel frame is completed, fill out the "Concealed Acceptance Form" and attach the "Canopy Steel Frame Structure Inspection Form" to report to the supervision unit for acceptance.

  1.1.3.9.面板安装待钢骨架安装验收完毕后,采用汽车吊及电动吸盘进行玻璃面板的吊装,利用满堂脚手架安装玻璃。

  1.1.3.9. After the installation and acceptance of the steel frame, the glass panel will be lifted using a truck crane and electric suction cup, and the glass will be installed using a full scaffold.

  (1)、在龙骨上重新弹设玻璃安装中心定位线,所弹墨线几何尺寸应符合要求,墨线必须清晰。

  (1) Re mark the glass installation center positioning line on the keel, and the geometric dimensions of the marked ink line should meet the requirements. The ink line must be clear.

  (2)、依据《雨棚玻璃编号图》,确定每块玻璃在雨棚上的位置,安装前位控制线,因雨棚钢结构总有一些不平整,玻璃支撑点处需进行调整垫平。

  (2) According to the "Rainshed Glass Number Diagram", determine the position of each glass on the canopy and install the front control line. Due to the unevenness of the canopy steel structure, the glass support points need to be adjusted and leveled.

  1.1.3.10.雨棚吊顶安装待注胶等防水密封措施施工完毕,采用满堂脚手架进行不锈钢格栅的安装。雨棚不锈钢格栅吊顶安装示意图

  1.1.3.10. After the installation of waterproof sealing measures such as glue injection for the canopy ceiling is completed, the stainless steel grating will be installed using a full scaffold. Installation diagram of stainless steel grille ceiling for canopy

  1.1.3.11.安装完成全部安装完成后,进行清洁处理,并做好成品保护标识,防止损坏。

  1.1.3.11. After the installation is completed, clean it thoroughly and label the finished product to prevent damage.

  本文由 济南停车棚&苍产蝉辫; 友情奉献.更多有关的知识请点击&苍产蝉辫; &苍产蝉辫;真诚的态度.为您提供为的服务.更多有关的知识我们将会陆续向大家奉献.敬请期待.

  This article is a friendly contribution from Jinan Parking Shed For more related knowledge, please click / Sincere attitude To provide you with comprehensive services We will gradually contribute more relevant knowledge to everyone Coming soon.

阅读/ Recommended reading

  很多人看到耐力板雨棚很漂亮,自己也想装,去了解耐力板雨棚的时候却又听到各种不一样的评价,有说不好用的,说两叁年就坏了开裂了,还发黄变色,有说挺好用的,已经用了十几二十年,而且很...

济南推拉棚:雨棚选什么样的,才会功能多,作用大? 2025-10-27
济南伸缩棚:看看大家常用什么样的雨棚 2025-10-25
济南雨棚阳光房款式大揭秘 2025-10-23
济南停车棚:塔楼底部的施工技术方案! 2025-10-21